PROJECTS  /  2016

Renewal of Domestic Water Supply to Eraring Power Station

In 2016 SNK Group was contracted by Origin Energy to carry out the upgrade to renew the portable water supply at Eraring Power Station.

Key features of this project were:

  • Assist in the design and approval process with HWC.
  • Assist the client with consultation of all involved parties; LMCC, HWC & Centennial Mandalong.
  • Carry out hot tap connections, whilst maintaining water supply to Mandalong Mine and Eraring Power Station.
  • Design and construct dual water supply system to ensure minimal interruption to daily activities.
  • Excavation and restoration of roadways.
  • Installation of backflow prevention devices to comply with HWC.

The project was completed successfully on time and within budget with zero incidents.

IMG_3053
IMG_3053
IMG_3054
2.2

Contact Form

Please fill out the enquiry form below and we will get back to you shortly. Please be as thorough as you can with your message so we assist you as effectively and as timely as possible.

Contact

Careers with SNK

We are frequently on the look out for talented and committed individuals to join our team.